large twn hm complex

I have my thoughts on how long this will take. Just Thought I would see your thoughts on time frame on clearing this property. skid loader with blade and trucks with 8.2 V's or boss 8' straight with boss plow extensions. don’t care about other types of equipment.. that’s the equipment that will be used out there. Would like to see thoughts by other contractors that have similar equipment and what they are thinking it would take them time wise! And yes I will be using more than one loader and more than one truck on this property. Just want base hours of completion So many hrs of loader work, so many hours of truck work. 236 driveways 25'Lx16'W 114,000sqft of roads Thanks

Name:  large town hm complex.jpg
Views: 256
Size:  95.4 KB
__________________
(The BOSS's) 08' 1 ton 4wd Dodge C.C, 6.7 CTD BOSS V
1992 Ford L8000 8ton dump truck with under tailgate spreader
lots of snow blowers and shovels
(1) John deere 455 / Blade
(2) Quads& plows
Bobcat S300
Bobcat T250
( An lots of good subs contractors that are realiable and hard workers) with out them our company would not be what it is today!!
Proud member of

Last edited by TPC Services; 10-24-2012 at 10:31 AM.
Reply With Quote
  #2  
Old 10-24-2012, 10:42 AM
plowman4life plowman4life is offline
Senior Member
 
Join Date: Jan 2008
Location: northeast
Posts: 558
if you have 236 driveways i would highly recomend a swingwing since that will cut your time in half.

1. 236 driveways figure 5 minutes per drive with a skid thats going to break down to 19 hrs or so.

2. sqft of roads is useless always measure it in lane miles. ( if you can break it down this way i can give accurate numbers)

3. 8' plow is going to require 2 passes minimum per lane mile in order to open the road (or4 passes total)
__________________
Owner Summit Landscaping LLC.
Reply With Quote
  #3  
Old 10-24-2012, 10:48 AM
TPC Services's Avatar
TPC Services TPC Services is offline
Senior Member
 
Join Date: Dec 2005
Location: Des Moines, IA
Posts: 879
sorry loader will have 8' blade also. 2.85 acres. or roughly 2.1 lanes miles. hum, I was think 3 pass with a V first pass down the middle and then two more to clear each side off to curb. these are twn hm roads so they are really not that wide. thats what it normal takes us pass wise. but hey each of us have their own proven way and there is nothing wrong with that. the guy that had it last year only used one truck and skid and it took him only 5hrs to clear it. I would really like to see what that place looked like done YIKES...
__________________
(The BOSS's) 08' 1 ton 4wd Dodge C.C, 6.7 CTD BOSS V
1992 Ford L8000 8ton dump truck with under tailgate spreader
lots of snow blowers and shovels
(1) John deere 455 / Blade
(2) Quads& plows
Bobcat S300
Bobcat T250
( An lots of good subs contractors that are realiable and hard workers) with out them our company would not be what it is today!!
Proud member of

Last edited by TPC Services; 10-24-2012 at 10:54 AM.
Reply With Quote
  #4  
Old 10-24-2012, 11:07 AM
plowman4life plowman4life is offline
Senior Member
 
Join Date: Jan 2008
Location: northeast
Posts: 558
i would say you bang that out in about 8-10 hrs. or so with 2 trucks and a skid. but that is still 24-30 man hrs.

it must have looked terrible with him doing it in 5 hrs.

most of your time is going to be in the driveways. i would say a big time saver would be putting 2 skids in there to do driveways. and running a 6 wheel dump through there to do the road. ( that would be what i would do since the dump with a 10-11 foot plow is going to clear the road in a few minutes.) 2 lane miles for a dump truck will be 15 minutes or so. a pickup will be easily 3 times that. JMO
__________________
Owner Summit Landscaping LLC.
Reply With Quote
  #5  
Old 10-24-2012, 12:33 PM
TPC Services's Avatar
TPC Services TPC Services is offline
Senior Member
 
Join Date: Dec 2005
Location: Des Moines, IA
Posts: 879
yes but you still have to worry about the trail offs that will flow over the open ends of those drives so my big single axel dump truck with a 11' blade will not work in there to well plus it will be a pain in the put will backing up all the time in those short shoot drives I may try it the first storm to see how well it works though. don't really use that truck to much for plowing just sanding&salting. I was around 10hrs for loader work and 6-8 truck time. but ever buddy runs there equipemtent a little bit differant. we don't run our stuff flat out nor are we going at a snails pace either, just nice and steady thanks for your input it was nice to see that instead of all the smart aleck remarks that are put on here anymore by alot of these guys.
__________________
(The BOSS's) 08' 1 ton 4wd Dodge C.C, 6.7 CTD BOSS V
1992 Ford L8000 8ton dump truck with under tailgate spreader
lots of snow blowers and shovels
(1) John deere 455 / Blade
(2) Quads& plows
Bobcat S300
Bobcat T250
( An lots of good subs contractors that are realiable and hard workers) with out them our company would not be what it is today!!
Proud member of

Last edited by TPC Services; 10-24-2012 at 12:54 PM.
Reply With Quote
  #6  
Old 10-24-2012, 02:23 PM
ryde307 ryde307 is offline
Senior Member
 
Join Date: Dec 2009
Location: Excelsior, MN
Posts: 757
A bit off topic but do you have to shovel?

I am asking this more a somewhat of a thread highjack. I am alot better at figuring a time for trucks and equipment than shoveling and have passed on some recent bids that were 70% or more shoveling partially because of that.

With an association like this how do you estimate time for shoveling?
By total SQFT or come up with a time per unit and multiply?
Reply With Quote
  #7  
Old 10-25-2012, 09:24 PM
TPC Services's Avatar
TPC Services TPC Services is offline
Senior Member
 
Join Date: Dec 2005
Location: Des Moines, IA
Posts: 879
Quote:
Originally Posted by ryde307 View Post
A bit off topic but do you have to shovel?

I am asking this more a somewhat of a thread highjack. I am alot better at figuring a time for trucks and equipment than shoveling and have passed on some recent bids that were 70% or more shoveling partially because of that.

With an association like this how do you estimate time for shoveling?
By total SQFT or come up with a time per unit and multiply?
My sqft, and high jack away sir as longs as its a meaningfull comment or question
__________________
(The BOSS's) 08' 1 ton 4wd Dodge C.C, 6.7 CTD BOSS V
1992 Ford L8000 8ton dump truck with under tailgate spreader
lots of snow blowers and shovels
(1) John deere 455 / Blade
(2) Quads& plows
Bobcat S300
Bobcat T250
( An lots of good subs contractors that are realiable and hard workers) with out them our company would not be what it is today!!
Proud member of
Reply With Quote
  #8  
Old 10-25-2012, 09:53 PM
WIPensFan's Avatar
WIPensFan WIPensFan is offline
2000 Club Member
 
Join Date: Jan 2009
Location: Southern WI
Posts: 2,338
TPC, can you post a closer view of that place? I can't tell where the snow will be put even.
__________________
09' Chevy 4x4 Pickup 6.0L 3/4Ton
07' Chevy 4x4 6.0L 1-Ton Dump / Blizzard 8611LP & Daniels 8'0 Pull Plow
98' Chevy 4x4 Pickup 7.4L 3/4Ton / Boss 8'2" V / Daniels 7'6" Pull Plow
Boss SmartHitch 1100 Tailgate Spreader
Bobcat S650 / Snow Wolf Ultra 120
Reply With Quote
  #9  
Old 10-26-2012, 06:56 AM
cet's Avatar
cet cet is online now
2000 Club Member
 
Join Date: Oct 2004
Location: Newmarket, Ontario
Posts: 5,803
I have been in a subdivison like this while the snow clearing is going on. I don't think a driveway will take any longer then 2 min. They were back dragging the drives with 1 skid with a blade and then pushing it up with a 2nd skid that had a push box on it. They had a F650 doing the roads and the whole thing went quickly IMO
Reply With Quote
  #10  
Old 11-06-2012, 01:20 PM
Wiedmann's Avatar
Wiedmann Wiedmann is offline
Member
 
Join Date: Oct 2012
Location: Prole, IA
Posts: 59
I'm interested in seeing what comes from this. I plan on placing a bid on a property similar this in size next year, a little smaller but it will give me an idea of how I should bid it.
Reply With Quote
  #11  
Old 11-06-2012, 04:52 PM
newhere's Avatar
newhere newhere is offline
Senior Member
 
Join Date: Oct 2009
Location: Fenton
Posts: 999
no way will a drive way take 5 minutes. Put a 8.5' wide rear facing box on the skid ( so the wings face the machine not out) and i bet you can do 2 drives per minute. Figure 3 hours to do all the drives. Have a v-plowed truck pushing the rows out to the end. Another 4-5 hours on a truck. Plus 1 more skid hour for clean up and stacking.
Reply With Quote
Reply

Bookmarks

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump





Powered by vBulletin® Version 3.8.6
Copyright ©2000 - 2013, Jelsoft Enterprises Ltd.
Copyright ©2000 - 2012 PlowSite.com™ Moose River Media
All times are GMT -5. The time now is 08:26 PM.

Page generated in 0.03164 seconds with 10 queries